Progressing well on Burlington Square
Work is progressing well on Burlington Square, week 53 of 98 and the drone shows the scale of the project in Manchester's University Quarter....
• SFS Installation to the external facades are underway.
• Window Install is ongoing to all areas to allow internal fit out to commence
• Apartment construction underway with plaster boarding and stud work ongoing internally to level 2
• Mechanical & Electrical 1st fixes are underway and are currently progressing onto Level 6
• Roofing works are ongoing to all areas to provide weather protection internally.
• Brickwork is ongoing to the external facades and internally to the stair / lift cores.
• Metal decking and floor slab construction are nearing completion in line with sequencing and programme
.